Oman Removes 5% Retention in Government Contracts and Tightens Rules on Project Delays
1. Overview
Oman’s Ministry of Finance, in cooperation with the Projects, Tenders and Local Content Authority, has announced a revised package of unified government contracts. The package introduces a new Design, Procurement and Execution Contract and updates the existing standard Construction Contract and Engineering Consultancy Contract.
The reforms aim to improve contractual clarity, accelerate project delivery, strengthen accountability and enhance the efficiency of government expenditure. The revised contracts are mandatory for government entities subject to Oman’s Tenders Law.
2. Key Changes
Abolition of the 5% retention requirement
The revised contracts remove the retention of 5% of the actual contract value previously withheld under the relevant contractual framework. The change is intended to improve contractors’ liquidity and facilitate the timely execution of projects.
Practical implication: Contractors should review their existing and forthcoming government contracts to determine how the revised provisions affect payment entitlements, cash-flow forecasts and financial planning. The published announcement does not, by itself, establish that the change applies retrospectively to existing contracts.
Stricter measures for project delays
The revised framework introduces specific intervention thresholds for delayed projects:
-
5% delay: The contractor must submit a recovery plan intended to return the project to its approved schedule.
-
15% delay: The contractor’s eligibility will be reviewed, potentially resulting in restrictions on participation in future government projects.
These thresholds introduce a more structured approach to project monitoring and corrective action. Contractors should maintain reliable progress records, identify critical-path risks early and document the causes of delays and mitigation measures.
Stronger local content and Omanisation obligations
The revised contracts expressly incorporate local content requirements, including the employment and training of Omani nationals and greater reliance on local suppliers and subcontractors.
Contractors should assess their procurement arrangements, subcontracting structures, workforce plans and documentary compliance procedures against the requirements applicable to each project.
Expanded force majeure provisions
The revised contractual framework broadens the concept of force majeure to encompass natural events, epidemics and pandemics. This provides greater clarity when exceptional circumstances affect project performance and supports a more balanced allocation of contractual risks.
The precise consequences of a qualifying event will depend on the applicable contract wording, notification requirements and relevant contractual procedures.
Enhanced powers of government project owners
The revised contracts provide employers with broader powers to withhold or suspend payments and exercise set-off rights, subject to the contractual controls.
Contractors should therefore pay particular attention to payment certification, contractual notices, supporting documentation, disputed amounts and the circumstances in which deductions or payment suspensions may be exercised.
3. Other contractual developments
The updated contracts also seek to clarify the allocation of responsibilities between project parties, reduce overlapping authority, limit variation orders and strengthen provisions relating to insurance, guarantees, project administration and dispute resolution.
The standard contracts have been organised into six sections covering the contract template, project-specific conditions, general conditions, scope of work and local content, price schedules, and contract management procedures.
Four additional standard contracts covering services, small-scale works and services, procurement, and manpower engagement were reported to be under development at the time of the announcement.
4. Recommended Actions for Businesses
Contractors, engineering consultants and businesses participating in government tenders in Oman should consider the following measures:
-
Review contract templates: Obtain the updated official forms and compare them with the versions currently used by the business.
-
Reassess cash flow: Update project budgets and payment forecasts to reflect the revised retention provisions, subject to the applicable contract.
-
Strengthen project controls: Implement internal escalation procedures before delays approach the 5% intervention threshold.
-
Improve delay documentation: Maintain contemporaneous records of progress, critical-path impacts, variations, instructions and events potentially giving rise to extensions of time.
-
Audit local content compliance: Review Omanisation, local procurement and subcontracting commitments.
-
Review payment protections: Assess the contractual provisions governing certification, suspension, withholding and set-off.
-
Update risk allocation: Revisit force majeure, insurance, guarantees, variation procedures and dispute-resolution mechanisms.
5. YLAW Perspective
The removal of the 5% retention requirement is a welcome development for contractor liquidity. However, the revised delay thresholds and enhanced employer powers indicate a stronger emphasis on measurable project performance and contractual accountability.
Businesses should not assume that the abolition of retention eliminates other contractual security requirements or that the revised terms automatically amend existing agreements. The applicable contract, implementation arrangements and any transitional provisions should be examined before determining the legal effect on a particular project.
YLAW advises contractors, developers, engineering consultants and other businesses operating in Oman on government contracting, tender compliance, construction disputes, contractual risk allocation and commercial dispute resolution.